Bitcoin miners have billion-dollar AI contracts. Who pays for construction?



Bitcoin miners have secured AI contracts worth billions of dollars, but the money needed to build the promised facilities is arriving through a separate set of agreements involving customer advances, equipment loans and guarantees that cover only specified obligations.

Summary

  • TeraWulf’s Anthropic leases carry approximately $19 billion in commitments across a 20-year term, with construction continuing into 2028.
  • Google’s Nov. 4 agreements cover specified Anthropic obligations, with support beginning after the corresponding building’s last data hall starts operating.
  • IREN closed $3.65 billion of GPU financing in June, combining borrowing with customer prepayments to fund most of a $5.81 billion equipment bill.
  • IREN reported a 6% blended debt cost for that financing, while its lower 3.31% funding calculation included customer advances.
  • A one-percentage-point change in annual interest on a hypothetical $3.5 billion balance changes the yearly bill by $35 million.

The contracts can make construction easier to finance. Their value to shareholders still depends on the cost of borrowing, the equipment the operator must buy and how soon a customer begins paying for an operational facility.

TeraWulf has obtained Google credit support for approximately $19 billion of Anthropic lease commitments, giving lenders another contractual source of protection as the former Bitcoin-focused operator builds facilities that are scheduled to begin entering service in late 2027.

TeraWulf’s Nov. 4 announcement says the arrangements support anticipated project financing at its Justified campus in Kentucky, where Fluor is handling engineering and construction for three buildings.

The agreement makes a recognizable name available to lenders assessing a long construction project. It leaves the operator with work to complete and financing terms to manage before a headline contract becomes a regular source of cash.

Other companies with roots in Bitcoin mining are solving that problem differently. IREN has combined a Microsoft customer prepayment with loans secured against GPUs and contracted payments, providing a comparison between a tenant’s promise to pay later and money available to meet equipment bills now.

The $19 billion contract arrives over years

The Anthropic lease is a 20-year arrangement. Dividing the approximately $19 billion headline value by that term produces a simple annual average of $950 million, before considering the actual payment schedule or the stages at which buildings enter service.

The calculation is useful because it puts the total into a unit that can be compared with annual costs. It is not a forecast of recognized revenue, operating profit or cash available to shareholders in any particular year.

An operator cannot use the full lifetime value to pay today’s contractor unless a customer advances money or a lender agrees to finance against future payments. Borrowing converts part of the expected cash flow into construction funding, with interest and repayment obligations attached.

A hypothetical $950 million annual receipt would have to cover whatever expenses the contract assigns to the operator before it became a return on invested capital. Maintenance, employees, insurance and debt service can sit between a customer payment and money available for another project.

The commercial agreement determines who supplies the computing hardware. A facility owner leasing equipped space has a different purchasing obligation from a cloud provider that must acquire the GPUs, servers and networking equipment used by its customer.

TeraWulf’s planned Kentucky financing package was reported in July as potentially combining leveraged loans and high-yield bonds. The reporting described a financing proposal, not evidence that the entire package had already been borrowed.

A loan announcement needs the same distinction. The maximum amount a bank makes available can exceed the amount drawn, while borrowing may depend on construction milestones, documentation and specified uses of proceeds.

Suppose an operator obtains a $1 billion facility but draws $200 million in its first construction stage. Interest on the borrowed balance and fees on unused availability can have different bases, so applying one interest rate to the entire advertised facility may overstate the immediate cost.

Conversely, counting only interest on the first draw can understate the eventual financing burden if the project requires the rest of the facility. A fair comparison follows the draw schedule through construction and the repayment schedule after operations begin.

The date a lease begins earning revenue matters just as much as its length. A signed agreement can remain economically valuable while producing little current revenue during procurement and construction.

Shareholders therefore need the lifetime commitment, the expected service dates and the remaining spending requirement together. Comparing only the contract value with a company’s market capitalization leaves out the capital that must be supplied to earn those payments.

Google’s support covers defined obligations

Google’s involvement is a credit agreement with conditions. TeraWulf’s September-quarter filing, filed Nov. 6, says the relevant backstop takes effect when the last data hall under the corresponding Anthropic lease begins operating.

Following specified payment defaults or insolvency events, Google can assume a lease or, in certain circumstances, permit termination and pay a fee. The fee declines over time, has limits linked in part to project financing and can be accompanied by an interest in the landlord subsidiary.

The disclosed protection concerns a customer failing to meet covered lease obligations. It does not promise reimbursement of every cost the developer incurs before completing the buildings.

A lender examining a hypothetical construction loan would ask which event activates the support. If a contractor needs payment before the guaranteed rent obligation becomes effective, the financing arrangement must address that intervening period.

The distinction has consequences for the price of debt. Protection against a tenant’s eventual failure can improve a lender’s expected recovery without removing concerns about procurement, delays or whether the borrower can complete the asset.

TeraWulf Chief Financial Officer Patrick Fleury called the “cost of capital” fundamental to infrastructure development in the company’s announcement. His argument is that stronger customer credit support can help the company obtain more competitive borrowing terms.

A lower interest bill would leave more project cash available after financing costs. Using a hypothetical $3.5 billion average debt balance, a reduction from 9% to 8% would save $35 million annually before fees or changes in principal.

Over five years, a constant $35 million annual saving totals $175 million without discounting. Actual savings would depend on how quickly debt is drawn and repaid, whether the interest rate floats and the cost of obtaining the support.

The strongest case for these agreements is therefore concrete. A credible guarantor can improve financing terms and make an otherwise difficult capital requirement more manageable.

The contractual limits remain important even when that case holds. A guarantor’s option to make a termination payment produces a different outcome from collecting every rent payment over the original lease term.

Project lenders may accept that alternative if it covers their exposure. Equity investors have a different concern because their expected return can include profits beyond the repayment of secured debt.

IREN’s equipment financing shows who supplies the cash

IREN’s Microsoft arrangement offers a separate example because the company is purchasing the computing equipment. Its original Microsoft agreement, announced Nov. 3, 2025, was valued at $9.7 billion over five years and included a 20% customer prepayment.

Twenty percent of $9.7 billion is $1.94 billion. The advance supplies funding before all the contracted service has been delivered, reducing the amount that must come from lenders or shareholders.

IREN subsequently closed GPU financing of $3.65 billion in June 2026. The company said the facility, combined with customer prepayments, covered $5.59 billion of a $5.81 billion GPU capital requirement.

Subtracting the two published totals leaves approximately $220 million, or 3.8% of that equipment bill, outside the described combination. The rounded 96% coverage figure concerns the stated GPU spending, not every expense across IREN’s development pipeline.

The combination answers the construction question in a way a headline contract value cannot. Some cash comes from the customer before service, some from institutions lending against equipment and contracted cash flow, and the residual has to be met through other available resources.

Customer advances still carry a commercial obligation. The provider must deliver the service for which the money was paid, and the relevant agreement governs consequences if delivery changes.

An advance should therefore not be treated as profit received before work begins. If a hypothetical customer pays $100 million toward future services, the operator has more cash available but still owes the agreed performance.

Equipment financing has another characteristic: a lender can take security over assets that are expensive to acquire and can change in value. The useful question is whether the repayment schedule is supported by the customer receipts attached to those assets.

Imagine a $500 million equipment loan repaid evenly over five years. Principal alone averages $100 million a year before interest, so a comparison that counts only the coupon would omit most of the annual cash repayment.

A facility with a large final repayment has a different profile. It may leave more cash available during early operations while requiring refinancing or accumulated cash when the balance falls due.

The comparison between TeraWulf and IREN is about these different funding structures. It does not establish that one contract produces a better investment return, because the operating assets, customer terms and costs are not identical.

The funding picture has since developed beyond the June facility. IREN’s Nov. 5 quarterly update reported $200 million in AI Cloud revenue for the September quarter and $28 million from Bitcoin mining, demonstrating that delivered computing services were already a substantial operating business.

The company moved its target for more than $4 billion of annualized run-rate revenue from year-end into January 2027, with a possible extension to February. It attributed the timing change to customer-requested changes and supplier timing, distinguishing an operating delivery issue from whether customers had signed contracts.

Run-rate revenue needs its own conversion. A hypothetical business operating at a $4 billion annualized pace for only one month would generate approximately $333 million during that month if the pace were constant, not $4 billion of recognized annual sales.

Starting that pace two months later reduces the months contributing at full scale within a financial year. It can leave the lifetime customer commitment intact while changing the timing of receipts available for debt payments and further construction.

IREN described the target as fully contracted and funded. That is the company’s affirmative case against a simple funding-shortfall argument, and it should remain attached to the specific capacity and assumptions covered by the statement.

A funded target is different from every project in a development pipeline being funded. Evaluating the next expansion still requires its equipment spending, commitments and customer terms, especially when it involves another campus or a different type of service.

The same November update set out $15 billion of remaining planned fiscal 2027 capital spending. IREN identified $9 billion of cash, committed GPU financing and prepayments, with another $6 billion targeted from financing and other sources subject to market conditions.

The definition of the $9 billion included restricted cash, undrawn facilities and contracted advances not yet received. It was therefore a funding category, not $9 billion of unrestricted cash already sitting in an account.

IREN’s disclosure draws the boundary at a specified development program: the specified program supporting the nearer revenue target was described as funded, while further capacity required additional targeted capital. Applying the funding claim to the entire expansion would erase the boundary IREN itself published.

The lower funding percentage includes a customer advance

IREN’s June announcement presented two percentages: a 6% blended cost of debt and a 3.31% average financing cost that included the customer prepayment as a zero-interest funding source. Both describe the company’s calculation, but they use different funding bases.

A simplified example shows why the distinction matters. Borrowing $60 at 6% produces $3.60 in annual interest; combining it with a $40 advance carrying no interest puts that same interest bill over $100 of funding, giving a blended 3.6%.

The lender still charges 6% on the loan in that example. The smaller blended number describes the funding package, not the price available to a company borrowing the entire amount.

IREN’s stated calculation uses weighted average balances over the contract term and excludes fees. Reproducing it exactly would require the underlying payment and amortization schedules, so the simple example is explanatory arithmetic rather than a reconstruction of its published rate.

Fees can be meaningful when financing is raised or replaced. A hypothetical 1% upfront fee on a $1 billion facility is $10 million, even before any periodic interest charge.

If that facility is used for one year, the fee has a different annual significance from a similar fee spread over a five-year borrowing. Comparing the coupon alone can conceal that difference.

IREN’s fiscal 2026 results described a separate $2.4 billion financing for a Mackenzie expansion at a fixed 9% rate. The company identified the associated customer deployments as non-investment-grade.

Applying 9% to $2.4 billion gives $216 million annually on an unchanged, fully outstanding balance. The calculation is not the company’s expected interest expense because actual balances and repayment dates can change.

It nevertheless demonstrates why customer quality and financing structure deserve space beside the revenue announcement. A three-percentage-point difference on the same hypothetical $2.4 billion balance is $72 million a year.

A company can reasonably accept a higher financing rate if contract pricing supports the cost. Without both the revenue terms and the capital requirement, the interest percentage alone cannot establish whether the development is attractive.

Investors comparing financing announcements therefore need the same units: interest on debt, cost across all funding, fees and the period over which balances remain outstanding. Mixing those measures can make one operator appear cheaper to finance simply because it received a larger customer advance.

Construction dates determine when the financing starts paying back

TeraWulf’s November announcement puts phased ready-for-service completions at late 2027 through the second quarter of 2028. Those are planned delivery dates, leaving a substantial period between the credit-support announcement and the full operating asset.

A six-month delay has an identifiable financing cost in a simplified case. If $1 billion remains outstanding at 8% for the additional half-year, the extra interest is $40 million before any other delay expense.

The effect is different if a facility has not been drawn or if the customer begins paying before final completion. The actual documents determine which party finances a delay and whether receipts continue during it.

A construction budget needs a distinction between work already completed, committed purchases and spending that remains uncontracted. Cash paid to a supplier can reduce the bank balance while securing equipment that will arrive later.

Contractors, suppliers and utilities can have separate payment milestones. A developer may need to fund several of them before the customer accepts a completed hall.

TeraWulf said Fluor’s agreement includes procurement oversight, open-book cost reporting and defined delivery milestones. Guaranteed maximum pricing was being established as engineering and procurement advanced, according to the company’s November statement.

A maximum-price provision can improve cost visibility, but its scope matters. Equipment changes requested by a customer or work outside the covered package may be treated differently under a contract.

Permits are another project-specific issue. TeraWulf said its existing New York developments were unaffected when the state paused new permits for certain data centers in July, despite a decline in its share price after the announcement.

The episode illustrates why a state-level restriction should not automatically be applied to every facility owned by a company operating there. Existing approvals and the actual terms of the measure determine which work is affected.

An operator announcing access to power still has to explain the form of that access. A completed connection, a utility commitment and an early development opportunity carry different construction requirements.

Customers paying for reliable computing capacity need an operating service at the agreed specification. The value of a site’s electricity connection is therefore linked to the additional work needed to turn it into usable capacity.

Bitcoin holdings can finance the transition, with a measurable limit

Selling Bitcoin is one possible source of development cash, but there is no basis for assuming every AI project requires it. Customer advances, secured borrowing and equity issuance can meet some or all of a particular company’s requirement.

The arithmetic becomes more demanding when the coin price falls. Raising $100 million at a hypothetical $100,000 per Bitcoin requires 1,000 BTC; at $60,000, it requires approximately 1,667 BTC before transaction costs.

The difference is nearly 667 BTC for the same dollar bill. A company relying on coin sales therefore faces a funding quantity that changes with the market even if its contractor’s invoice remains fixed.

Operating mining receipts introduce another variable. A miner can sell newly produced coins as part of ordinary cash management without reducing a previously accumulated treasury by the same amount.

TeraWulf’s history shows why dated balance-sheet descriptions matter. The company repaid a term loan of $77.5 million in July 2024, when it described eliminating its outstanding debt.

Subsequent financing transactions changed the position described in July 2024. Using that dated debt-free description in a November 2026 assessment would omit obligations taken on during the intervening expansion.

Ethereum co-founder Vitalik Buterin highlighted another difference in October when he compared computing costs across mining and AI inference. The estimates he shared put computing capital spending at roughly 76% of inference costs and electricity at 45.9% of the mining comparison.

Buterin’s comparison concerns the composition of costs, with a much larger computing-capital share in the AI estimate. Applying the percentages to a particular operator would require its own equipment and service model.

A miner buying its own GPUs must finance that equipment in addition to the site. A landlord supplying power and facilities may leave more of the hardware bill with its tenant, depending on the lease.

New equity has a different cost from selling existing Bitcoin. It can preserve corporate cash while dividing future earnings and assets among more shares.

For example, a company with 100 million shares that issues another 20 million increases its share count by 20%. An existing holder’s fraction of the company falls by one-sixth if the holder buys no new shares, although the company receives the proceeds and may create value with them.

Evaluating that transaction requires the price of the new shares and the return on the assets funded. Dilution alone does not establish value destruction, just as preserving the Bitcoin treasury does not establish good financing.

A profitable project still has to leave cash for shareholders

The company’s customer can pay every invoice while shareholders earn less than expected if construction costs or financing charges absorb more of the proceeds. Contract performance and equity return are related, but they are not interchangeable measures.

Consider an illustrative project generating $200 million annually after operating costs but before financing. If annual interest and principal payments total $150 million, the remaining cash is $50 million before taxes and other obligations.

If the same project requires $50 million of recurring equipment spending, little may remain for distributions despite the positive operating result. The example is a cash-flow exercise, not an estimate for either company covered here.

Removing principal repayments from that calculation would make the apparent surplus much larger. Replacing principal with depreciation would answer an accounting question without showing the same cash requirement.

A long lease can support borrowing precisely because payments are expected to continue over many years. Financing the asset allows the operator to spread its initial cost across those receipts.

The favorable case is strongest when contracted payments exceed operating and financing expenses by a comfortable amount, construction stays within budget and the asset begins service when planned. A customer advance can further reduce the cash shareholders must supply upfront.

Credit support strengthens that case when it improves the amount or price of funding available. A financing discussion that treats guarantees only as evidence of weakness would miss the reason developers seek them.

The unresolved question is the return after the whole funding arrangement has been paid for. Announced capacity and lifetime revenue do not provide all the inputs needed to calculate it.

Corporate share ownership requires similar care. A Nov. 18 review of institutional holdings in miners listed Swiss National Bank positions in IREN, Hut 8, Riot and TeraWulf based on Sept. 30 filings.

The Sept. 30 holdings record equity positions in the operators. They do not identify construction loans supplied by those investors or commitments to finance the companies’ next developments.

A share can change hands between investors without sending money to the company. Construction funding reaches the operator through primary issuance, customer payments, borrowings or cash already available on its balance sheet.

Funding announcements need to be followed through to delivery

IREN’s March fleet announcement shows how many funding routes can appear in one development plan. The company said it had secured $9.3 billion through customer prepayments, convertible notes, GPU leasing and GPU financing over the preceding eight months.

Its GPU expansion plan identified approximately $3.5 billion of additional second-half 2026 spending across equipment, labor and related items. Purchase agreements and expected capacity were distinct from delivered, revenue-producing infrastructure.

Adding every financing headline can double-count money if an earlier facility is replaced by a later transaction. A refinancing often supplies cash to repay the original lender, leaving less new funding than the gross issuance suggests.

A hypothetical $1 billion bond used to repay an $800 million construction loan produces only $200 million before fees for other uses. Reporting $1.8 billion as simultaneously available would count the same project financing twice.

The same discipline applies to cash that is restricted for a particular project. A bank balance reserved under a financing agreement cannot automatically be assigned to another campus without checking the conditions on its use.

A useful funding reconciliation starts with unrestricted cash, adds committed and drawable financing, subtracts repayments and near-term obligations, and compares the result with remaining spending. It keeps equipment financing separate where the proceeds cannot be used for general construction.

None of those calculations requires assuming that AI demand will collapse. Even a fully booked project can encounter a mismatch between the dates bills fall due and the dates customer receipts become available.

Conversely, evidence of funded construction, accepted facilities and timely customer payments would weaken concerns about that mismatch. Those are observable milestones, unlike treating every large AI contract as either guaranteed profit or a speculative promise.

The remaining disclosure question is specific: how much capital is still needed, from whom, on what terms and before which delivery date? A company that answers those points lets investors compare the next announcement with the cash requirement already on record.

Under the November schedule published for Justified, phased completions begin in late 2027 and continue through the second quarter of 2028.

What to Watch

  • Project financing: The amount actually borrowed, repayment schedule, fees and collateral attached to each campus, separated from undrawn commitments and refinancing proceeds.
  • Customer advances: Cash received before service, the equipment or construction bills it funds and the delivery obligations that remain after payment.
  • Guarantee activation: The commencement conditions, covered defaults and termination-payment provisions in Google’s support agreements with the relevant landlord subsidiaries.
  • Construction progress: Procurement, approved budgets, accepted data halls and any changes to the late-2027 through second-quarter-2028 Justified timetable.
  • Shareholder funding: New shares, convertible obligations and disclosed Bitcoin sales used to meet development costs, measured against the cash they actually supply.

FAQs

Does a $19 billion AI contract give TeraWulf $19 billion to spend now?

No. The headline describes commitments over the lease term, while construction bills fall due on a different schedule. Funding must come from available corporate cash, customer advances, financing or other disclosed sources. The annual average calculated here is not a prediction of any particular year’s revenue.

What has Google agreed to cover?

The disclosed arrangements cover specified Anthropic obligations under the relevant leases. They include conditions for activation and alternatives following covered defaults. They should not be described as an unrestricted guarantee of all TeraWulf debt or every construction expense.

Why do customer prepayments matter?

An advance supplies cash before all contracted services have been delivered, reducing the amount needed from other sources. The operator still owes the customer its agreed performance. Customer-funded construction can improve financing economics without making the payment immediate profit.

Why does IREN show both 6% and 3.31% financing figures?

The first describes its stated blended debt cost, while the second includes customer prepayments in the funding calculation. The lower figure therefore uses a different denominator and assumptions. A reader cannot apply it as the interest rate on every dollar borrowed.

Will miners have to sell Bitcoin for AI development?

Some operators can use coin sales, but the requirement depends on their funding plans and available cash. A customer advance or equipment loan can reduce that need. Any claim about a particular company should be tied to its disclosed transactions and remaining commitments.

Does project debt always put the parent company at risk?

The answer depends on the borrower, collateral, guarantees and contractual recourse. A subsidiary financing can contain protections that differ from corporate borrowing. Calling a facility project financing alone does not establish how much support the parent has promised.

Is a large contract enough to establish that the project is profitable?

The contract needs to be assessed alongside construction, operating and financing costs. Cash available after interest can still be needed for principal repayments or equipment replacement. Profitability and the amount distributable to shareholders require more information than lifetime revenue.

What evidence would ease the funding concerns?

Committed capital matched to remaining spending, completed facilities and customer payments would make the financing path more visible. Favorable borrowing terms and costs within budget would strengthen that evidence. This is educational analysis, not investment advice.

Disclaimer: This article is for information and educational purposes only and does not constitute financial or investment advice. Figures reflect regulatory filings and reporting available at the time of writing and change with each disclosure. Nothing here is a recommendation to buy, sell, or hold any security or asset. Always do your own research. Information is accurate as of Nov. 19, 2026. Legal and tax questions should be discussed with qualified professionals.